Client
Leeds City Council

Principal Contractor
Freyssinet Makers

Contract Value
£1M

Contract Duration
30 Weeks

Completion
February 2008

PDF Download

Further to the successful completion of work at Poplar Court Leeds, Freyssinet Makers carried out repair works to a further four tower blocks for Leeds City Council.

Works consisted of:
• External repairs
• Coatings
• Roof insulation
• Cavity wall insulation
• Asphalt roofing

The works were carried out to programme and with minimal disruption to owners and tenants.

All external works were carried out from suspended cradle access to alleviate security problems.

The client and occupiers were delighted with the standard of work and a letter of commendation was received from the Tenants Association.

 