Leeds City Council
Principal Contractor
Freyssinet Makers
Contract Value
£1M
Contract Duration
30 Weeks
Completion
February 2008
Further to the successful completion of work at Poplar Court Leeds, Freyssinet Makers carried out repair works to a further four tower blocks for Leeds City Council.
Works consisted of:
• External repairs
• Coatings
• Roof insulation
• Cavity wall insulation
• Asphalt roofing
The works were carried out to programme and with minimal disruption to owners and tenants.
All external works were carried out from suspended cradle access to alleviate security problems.
The client and occupiers were delighted with the standard of work and a letter of commendation was received from the Tenants Association.
Freyssinet Makers, 46 Deerdykes View, Cumbernauld, Glasgow G68 9HN Phone +44 (0) 1236 780622 Fax +44 (0) 1236 780722 Email info@freyssinet.co.uk