Euro Tunnel
Principal Contractor
Vinci Energies / Eurovia Travaux Ferroviaires / Freyssinet Consortium
Contract Value
50 million Euro
Freyssinet Value
20 million Euro
Work Completed
January 2009
Following severe fire damage in September 2008, Channel Tunnel operator Eurotunnel awarded the repair contract to a consortium of Freyssinet, Eurovia Travaux Ferroviaires and Vinci Energies, that was charged with undertaking one of the most complex repairs to a tunnel that the world has ever seen, at over 1 kilometre into the Channel Tunnel.
Freyssinet was appointed to complete the civil engineering works, while ETF would be responsible for track and overhead wire restoration and Vinci Energies responsible for other equipment.
The extensive repairs included considerable amounts of hydro-demolition, using high-pressure water jets to remove concrete from various structures, which was specified as the method to remove the fire damaged concrete.
Concrete was then reinstated using sprayed concrete techniques by Freyssinet’s skilled operatives, with extensive tunnel strengthening also being required.
Freyssinet carried out intial strengthening of the tunnel using 1003 rock bolts to prevent tunnel roof collapse.
After this initial phase Freyssinet employed four hydro-demolition units to extract all of the fire damaged concrete.
This initial work took a total of six weeks, followed by a period of intense activity working from a two tier scaffold. All surveying and monitoring was undertaken by the site teams.
The final phase for Freyssinet was the spraying of over 4000 tonnes of sprayed concrete in 32 days, a record for this sort of work. Further works were then completed by the consortium.
This very successful and well planned contract was completed to the satisfaction of all involved.
Freyssinet Ltd. Innovation House, Euston Way, Town Centre, Telford, Shropshire, TF3 4LT Phone +44 (0) 1952 201901 Fax +44 (0) 1952 201753 Email rail@freyssinet.co.uk