FREYSSINET COMPLETE STRENGTHENING WORKS AT HAMMERSMITH FLYOVER IN TIME FOR THE LONDON OLYMPICS 20 June 2012

Hammersmith Flyover is an elevated roadway in west London which carries the A4 dual carriageway over the central Hammersmith gyratory system. Completed in 1961, it is one of the first examples of an elevated road constructed using reinforced post-tensioned concrete.

1-102_0499-300x192

Routine and special inspections revealed a significant corrosion problem with the existing post-tensioning installed in the early 1960’s. This necessitated an emergency closure of the bridge just before Christmas 2011 to allow further investigations. The bridge was re-opened a few weeks later in early January but with reduced load limits and lane closures. In December 2011 Freyssinet were appointed by Amey to assist with the design phase. Various options were considered to strengthen the bridge, with a target to complete the work in order to open the bridge to full traffic prior to the 2012 London Olympic Games. The solution adopted was to install additional post-tensioning (PT) tendons above and below the top slab within a new widened central reserve. The post tensioning was required to be durable, replaceable and adjustable (re-stressable) – all of which are satisfied by the Freyssinet C-Range ‘System 2’ pre-stressing system. Freyssinet were awarded the contract to supply and install the additional post-tensioning, valuing approximately £4 million. They commenced work on site in late January 2012, with the removal of around 200m of the existing concrete central reservation using hydrodemolition and wall sawing techniques. Works progressed well on site using a double shift pattern helped by unseasonably fine weather in February and March.

2IMG_0061-300x225

Once the reservation had been removed, a survey of the existing reinforcement in the deck was completed. An additional top slab was cast in the central reserve. Freyssinet carried out coring for the installation and stressing of vertical post tensioning ‘Freyssibars’, and cast new post tensioning concrete blisters above and below the top slab.

3sans-titre2-300x199

Freyssinet’s skilled post tensioning operatives then installed and stressed horizontal 19C15 tendons, un-bonded in pre-grouted HDPE (High Density Polyethylene) ducts. After stressing operations were complete, the Freyssibar ends were finished and capped and treated with corrosion protection.

4IMG_0154-225x300

Freyssinet had operatives working around the clock and contributed to over 30,000 hours being worked on site without a reportable incident. A dedicated health & safety advisor help to ensure that any safety issues were dealt with quickly and that there was good safety co-ordination with the Principal Contractor.

5IMG_0092-225x300

At the height of the work Freyssinet employed up to 80 operatives, supervisors and managers. Using specially developed formwork and post tensioning support systems they were able to remain ahead of the target programme and finish well ahead of a challenging programme in a race to reopen the flyover in time for the London Olympics. Freyssinet works were completed in early May 2012. The works completed to date bring Hammersmith Flyover back to full load capacity, and it was re-opened on May 28th 2012.