FIRE DAMAGE REPAIR SCHEME – M6 TOLL DUNTON LANE 07 August 2014

Following a lorry fire under the M6 Toll at the Dunton Lane underbridge, significant structural damage had occurred and the M6 Toll engineering team contacted Freyssinet to attend site and assist with the assessment of the damage and work with their design team to produce a suitable repair strategy.
To facilitate the clients key dates for re-opening of the M6Toll, it was necessary to install a central dividing screen on the scaffold. This allowed hydrodem to be undertaken on the East side of the structure whilst spray concrete was being undertaken concurrently on the west side. This made significant time savings to the overall scheme and ensured that the M6 Toll was re-opened in a timely manner.
Water produced during the hydro-dem process was treated on site prior to discharge into the adjacent storm drainage network. The Environment Agency provided consent to discharge prior to the commencement of the works. The water was filtered through geotextile before being PH tested and balanced to PH6-9 before discharge. Following the completion of the hydro-dem process, timber battens were installed to line and level by the joiners prior to spray concrete application.
During the sprayed concrete process, as a consequence of the attention to detail and competence of the spray concrete team, a very high level of quality was achieved with no voids at edges of repairs or behind reinforcement.
The Southern side wall of the structure had sustained surface damage during the fire, but due to the depth of the reinforcement (approx 85mm of cover) there had not been any significant structural damage/exposure of reinforcement to the south wall. The main function of the wall repairs was to restore a suitable ‘finish’ to the concrete surface. The conventional method of undertaking spray concrete repairs is to expose the existing reinforcement in order to allow the spray concrete to bond behind the bars and provide sufficient integrity of the repair. Due to the depth of the reinforcement it was not cost effective to remove the concrete behind rebar, so Freyssinet suggested that the existing concrete was treated with surface preparation by hydro-dem methods to provide a rough surface (CSP 6) which would allow spray concrete to bond to the substrate. Then a layer of reinforcement was introduced to the outer surface of the parent concrete in the form of A393 mesh drilled held in place with drilled and resin fixed 16mm L-bars.
Once the rebar was fixed, timber battens were installed to line and level by the joiners prior to spray concrete being applied. Once the sequenced wall repairs were complete, a ‘flash coat’ of spray concrete was applied to the walls and soffits in order to achieve a uniform textured finish. This was mainly for aesthetic reasons to cover the construction joints.
Whilst the North wall of the structure had not sustained a large amount of damage, there were a limited amount of localised repairs that were treated using flowable repair concrete methods rather than spray concrete.
Hydrodem was used to remove the defective concrete from these repair areas. Through the high level of attention to detail applied by the hydrodem team these repairs were broken out to a very high standard.