CONTINUED COLLABORATION WITH CONTRACTOR BYRNE GROUP 04 February 2011

Following the successful completion of the Olympic Media Centre and Knightsbridge Palace Hotel, the Freyssinet-Byrne relationship has been further enhanced with the award for the post tensioning to Southmead Hospital, Bristol.
The first post tensioned slabs for this £430million, 800 bed, state of the art hospital got underway in December 2010.
The 54000sqm of suspended slab spread over 6 levels and containing 300tonnes of bonded post tensioning is expected to be complete within a 45week programme.