Bridge Deck Strengthening & Concrete Repair – M5 Northway Decks

bridge deck strengtheningBridge Deck Strengthening & Concrete Repair

Client
Highways Agency

Principle Contractor
Amey

Value
£1,000,000

Contract Duration
25 weeks

Works Completed
January 2011

PDF Download

Freyssinet Limited was appointed to carry out bridge deck strengthening works on two bridges situated to the north of Junction 9 of the M5 motorway near Tewkesbury.

Northway Lane Bridge and Northway Back Lane Bridge structures both have a continuous four span voided reinforced concrete deck supported on slender columns. These columns were previously strengthened and further works were considered necessary to strengthen the bridge deck on each structure also.

Freyssinet was responsible for all associated works on site, including site set up, traffic management and the installation of scaffold platforms to allow the works to be completed safely.

The scope of works involved the installation of additional shear reinforcement in the form of vertical stainless steel dowel bars in the ribs of the decks.

Initial surveys were carried out by Principle Contractor Amey to identify and locate the upper and lower steel reinforcement materials and allow the position of the voids to be marked out on the soffit and deck prior to drilling. Voids within the deck were also be established by drilling 25Ø trial holes.

Cores were drilled at the marked locations and approximately 700no vertical bars were then installed and the holes grouted to seal the bars and provide a bond between the bar and the existing concrete.

This contract forms part of the Construction Management Framework for the Highways Agency Area 9 and 10.

The CMF is a collaborative approach to maintaining £75billion worth of assets for HA in these areas over the next four years. It consists of a number of different contractors from different specialist areas who work together to deliver network improvement and maintenance schemes on the all purpose trunk road and motorways in Area 9 and 10.

Following a comprehensive application process, Freyssinet was selected as the specialist contractor for concrete repairs and cathodic protection (in a joint venture with its sister company Corrosion Control Services Limited).

The CMF began in January 2010, and the contract will run for four years with a possible two year extension.

1 Drilling cores in the bridge deck
2 Installing the stainless steel dowel bars
3 View of the soffit
4 The holes were grouted to seal the bars