Monthly Archive: November 2016

Post-Tensioning, Strengthening and Concrete Repair – Hammersmith Flyover, Phase Two

Post-Tensioning, Strengthening and Concrete Repair Client Transport for London Main Contractor Costain Value £20 million Works Commenced December 2014 Works Completed Summer 2015 PDF Download Hammersmith Flyover is an elevated roadway in West London which carries the A4 dual carriageway over…
Read more

Bridge Refurbishment – Ketley and Dawley Bridges, M54, Telford

Sprayed Concrete, Hydrodemolition, CP, Freyssibar Installation Client Highways Agency Principal Contractor Amey Works Commenced July 2013 Works Completed March 2014 PDF Download Ketley and Dawley bridge refurbishment scheme on the M54 Telford was undertaken by Freyssinet between July 2013 and March…
Read more